2 Years ago, it was time to change to a new data historian. Stanford University utilities had been metering energy use since before 1940 and we needed a new system to hold all that information. AVEVA PI System has been integrated and has been a vital tool in optimizing energy use from the power plant where it is produced, all the way to the building where customers use the energy.
Over 2 years ago, Stanford’s powerplant needed to double its cooling capacity and also transition away from a DDC system managing operations. By implementing AVEVA System Platform, there was a great leap forward in system operations and control. This allowed us to achieve total system energy control and optimize the system to its true potential. ASP’s flexibility has enhanced the plant efficiency and helped the campus achieve sustainability goals, while seamlessly integrating diverse controls components.